Solar Case Study

Location: Metro San Diego

Roof Mount Solar Array

Utility: SDG&E Commercial TOU Rate

 

Solar PV Rating

Power Rating:

Power Rating:

Solar Cash Sale

Total Project Cost

Rebates and Incentives

Net Payments

Year 1 Electricity Savings

Payback

Total Electricity Savings

Levelized Cost Of Energy PV/kW

Power Purchase Agreement

Total Project Cost

Rebates and Incentives

End of Term Payment

Year 1 Payments

Year 1 Electricity Savings

Year 1 Net Savings

Net Payments

Total Electricity Savings

Levelized Cost Of Energy PV/kW

 

175 W DC

156 W AC-CEC

 

$592,600

($402,369)

$190,231

$45,350

4.19

$1,467,450

$0.050

 

$0

$0

$65,000

$42,300

$45,350

($3,050)

$1,106,277

$2,578,312

$0.162